Codelco Profit Surges Fourfold as Higher Copper Prices Offset Output Decline
Codelco reported first-half 2026 pre-tax profit of $1.97 billion as its realized copper price climbed to 653.2 cents per pound, offsetting an 11% decline in the Chilean miner's own copper production and higher operating costs.
By Paul Ploumis
Published August 31, 2026
Key Points
- Codelco's first-half pre-tax profit rose to $1.97 billion from $429 million a year earlier.
- The company's realized copper price increased to 653.2 cents per pound from 461.7 cents.
- Codelco's own copper production fell 11% to 564,000 metric tons from 634,000 tons.
- Operational constraints at El Teniente, weaker Chuquicamata output and declining ore grades at Ministro Hales weighed on production.
- Codelco has not issued an updated 2026 production forecast and is unlikely to meet its previous 1.33-1.36 million-ton target.
MONTREAL (Scrap Monster): Chilean state-owned copper producer Codelco recorded a sharp jump in first-half 2026 earnings, driven by a strong rise in copper prices despite lower mine output and increased operating costs.
The miner reported pre-tax profit of $1.97 billion for the January-June period, compared with $429 million a year earlier. Codelco said the stronger financial performance was largely supported by favorable copper prices.
The company's realized copper price surged to 653.2 cents per pound from 461.7 cents, providing a substantial boost to profitability.
Higher Copper Prices Offset Lower Mine Output
Codelco's own copper production dropped 11% to 564,000 metric tons from 634,000 tons in the first half of 2025.
The decline was mainly attributed to operational constraints at El Teniente, weaker production at Chuquicamata and declining ore grades at Ministro Hales.
El Teniente Challenges Add Pressure
Production challenges have intensified at El Teniente following a fatal accident in late July that claimed six lives.
The company has also temporarily halted development work at the mine's Andes Norte section because of concerns over seismic conditions.
2026 Production Target Faces Pressure
Codelco did not provide an updated 2026 production forecast in its latest results. The company is unlikely to meet its previous target of 1.33-1.36 million tons.
Meanwhile, the company's new CEO, Jorge Gomez, has identified restoring productivity as a key priority.
By 