Millar Western Indefinitely Shuts B.C. Pulp Mill, Putting 90 Jobs at Risk
Millar Western has indefinitely suspended operations at its Quesnel River Pulp mill in British Columbia, citing weak market conditions and uncertainty over economically viable fibre supplies. Approximately 90 workers have been affected.
Key Points
- Indefinite curtailment: The Quesnel River Pulp mill has been idle since September 4, 2026.
- Employment impact: Approximately 90 workers are affected, with severance and other assistance planned.
- Production capacity: The facility can produce approximately 375,000 air-dried metric tonnes of softwood pulp annually.
SEATTLE (Scrap Monster): Canadian forest products manufacturer Millar Western Forest Products has announced an indefinite curtailment of operations at its Quesnel River Pulp mill in British Columbia, following a prolonged shutdown that began in September.
The facility, which has an annual production capacity of approximately 375,000 air-dried metric tonnes of softwood pulp, has remained idle since September 4. An initial November 1 restart target was subsequently postponed to December 1 before management decided against resuming operations under current market conditions.
In a November 9 letter to employees, Executive Chair and CEO Karl Meyers said the company had reviewed its alternatives and concluded that an indefinite curtailment was the only commercially viable option.
Approximately 90 Workers Affected by Shutdown
The decision affects approximately 90 workers previously impacted by the temporary shutdown. Millar Western plans to provide severance compensation, continuation of certain benefits and employee assistance resources.
The company will also consider displaced employees for available positions at its other operations.
Remaining activities will be wound down over the coming weeks, although the company intends to preserve the possibility of restarting the facility. Its effluent treatment system will continue operating for up to 12 months or until an acceptable alternative arrangement is reached.
SCRAPMONSTER EDGE | CANADIAN FORESTRY INDUSTRY
Another Major Loss for B.C.'s Pulp Industry
The Quesnel curtailment follows Canfor's decision to permanently close its Northwood pulp mill, removing approximately 300,000 tonnes of annual production capacity, and Domtar's indefinite shutdown of its Howe Sound facility.
Together, the announcements highlight continuing pressure from weak pulp prices and limited access to economically viable wood fibre.
Industry takeaway: A recovery in pulp prices alone may not be sufficient to restore production. Reliable fibre supply, operating costs and export-market conditions will remain critical factors in determining whether curtailed mills can restart.
Local Economy Faces Further Pressure
The shutdown represents another setback for Quesnel, where forestry operations support contractors, transportation companies and other local businesses.
British Columbia premier-designate Lorne Doerkson described the announcement as a serious blow to workers and their families, while acknowledging that restoring operations would require addressing underlying fibre supply challenges.
Millar Western, owned by U.S.-based Atlas Holdings, operates three pulp mills in British Columbia and Alberta, with combined annual capacity of approximately one million tonnes.
The company has not confirmed when operations at Quesnel River Pulp might resume. Any restart will depend on market recovery and access to economically viable fibre supplies.
Also Read
Ontario Provides C$5.1 Million Boost for Espanola Pulp Mill Restart
Canfor to Shut Northwood Pulp Mill, 300 Jobs at Risk
Sources: Lesprom, November 11, 2026; The Canadian Press, November 9, 2026.