Grasberg Copper Mine Ramps Up to 67% Capacity After Disruption

Mining News  |  2026-10-05 06:45:44

Grasberg produced approximately 830 million pounds of copper and 230,000 ounces of gold in the third quarter.

Grasberg Copper Mine Ramps Up to 67% Capacity After Disruption
Summary
  • Grasberg recovery reaches 67% capacity
    Freeport-McMoRan’s Grasberg operation in Indonesia processed about 140,000 tonnes of ore per day in the third quarter, reaching roughly 67% of normal milling capacity. The recovery follows the fatal mud-flow disaster that shut the operation last year.
  • Full production targeted by end-2027
    Freeport expects Grasberg to reach approximately 80% of capacity by mid-2027 and return to full production by the end of 2027. Rehabilitation work includes upgrades to the underground material-handling system and the planned restart of Production Block 1S.
  • Strong copper and gold output supports recovery
    Grasberg produced about 830 million pounds of copper and 230,000 ounces of gold during the third quarter. Freeport expects copper sales of nearly 750 million pounds and gold sales of around 100,000 ounces, while the restart of its East Java smelter adds further support.

SEATTLE (Scrap Monster): Freeport-McMoRan’s Grasberg copper-gold operation in Indonesia continued its recovery in the third quarter, with milling rates reaching about 67% of normal capacity. A fatal mud-flow disaster in September last year had killed seven workers and shut the operation.

The Central Papua complex processed approximately 140,000 tonnes of ore per day during the quarter, slightly exceeding market expectations. Freeport expects the operation to reach around 80% of capacity by mid-2027. Also, full production is expected to be achieved by the end of 2027.

RELATED NEWS:

Freeport Targets Full Grasberg Mine Output by End-2027

Copper Spikes as Freeport Declares Force Majeure at Grasberg Mine

According to the company, rehabilitation work is advancing, with upgrades to the underground material-handling system scheduled for completion in early 2027. Freeport also plans to restart Production Block 1S around mid-2027, which will support the next phase of the production ramp-up.

Grasberg produced approximately 830 million pounds of copper and 230,000 ounces of gold in the third quarter. The company expects its copper sales to touch nearly 750 million pounds, while gold sales are expected to reach around 100,000 ounces.

Freeport also reported progress at its East Java smelter, which restarted in August. The company expects higher copper prices to help offset some of the financial impact during the recovery period.

Frequently Asked Questions


  • How much of Grasberg’s normal capacity did Freeport achieve in Q3?
  • Freeport-McMoRan reported that Grasberg reached approximately 67% of normal milling capacity during the third quarter. The operation processed around 140,000 tonnes of ore per day, slightly exceeding market expectations.

  • When is Grasberg expected to return to full production?
  • Freeport expects the operation to reach roughly 80% of capacity by mid-2027, with full production targeted by the end of 2027. Rehabilitation and infrastructure upgrades will play a key role in the production ramp-up.

  • What did Grasberg produce in the third quarter?
  • The mine produced approximately 830 million pounds of copper and 230,000 ounces of gold. Freeport expects copper sales to approach 750 million pounds and gold sales to reach approximately 100,000 ounces.