Modern Mining Plans Its First Commercial-Scale E-Waste Gold Plant, With Capacity for About 40,000 Gold Equivalent Ounces a Year

E-waste Recycling  |  2026-11-19 00:14:17   |   By

The world generated a record 62 million tonnes of e-waste in 2022, up 82% from 2010, according to the Global E-waste Monitor 2024, and the U.S. is the world’s second-largest generator.

SEATTLE (Scrap Monster): Modern Mining Technology Corp. (NYSE American: MDRN) (“Modern Mining” or the “Company”), which recovers gold, silver, copper and other valuable metals from electronic waste using a proprietary aqueous-based process, announced today it has laid out an 18-month plan to build its first commercial-scale operation in North Carolina, designed with an annual capacity to produce approximately 40,000 gold equivalent ounces. The plan follows the Nov. 12, 2026, closing of the Company’s approximately US$40 million initial public offering (“IPO”).

Modern Mining has proven it can recover and sell metal concentrate from electronic waste. Its Greenville, North Carolina, R&D demonstration facility has done so since November 2023, settling 41 product lots between December 2023 and June 2026. Next comes commercial scale: plant build-out, binding e-waste supply contracts and operator training, followed by commissioning and ramp-up.

“We approach electronic waste with the mindset of a mining company, as an above-ground resource rather than simply a waste stream,” said Jeet Basi, President and CEO of Modern Mining. “Building our first commercial-scale plant is the step that turns that resource into a new source of supply for the U.S. market. We designed our model so that each pre-concentration plant we add can feed the same purification hub, giving us a clear path to growth.”

Electronic waste is a large and growing source of valuable metals. The world generated a record 62 million tonnes of e-waste in 2022, up 82% from 2010, according to the Global E-waste Monitor 2024, and the U.S. is the world’s second-largest generator. The Company estimates that the e-waste it sources can deliver metal grades approximately 100 times higher than traditionally mined ores, and believes its process offers a cleaner, safer and lower-cost alternative to traditional mining.

From Build-Out to Revenue: The 18-Month Plan

The Company’s development targets, measured from completion of the IPO, are:

  • First 6 to 9 months: Complete build-out of a pre-concentration plant and an aqueous purification plant in North Carolina, convert e-waste supply arrangements into binding contracts, and train operating teams. The pre-concentration plant’s target design processing capacity is up to one tonne of waste printed circuit boards per hour.
  • Months 9 to 12: Complete commissioning and demonstrate ramp-up toward the pre-concentration plant’s target design capacity, addressing process bottlenecks as needed.
  • Months 12 to 18: Grow commercial production and revenue.
  • In parallel, months 6 to 18: Seek R2 (Responsible Recycling) Standard certification and add e-waste supply contracts to support operation at target design capacity.

Modern Mining plans to secure supply contracts with recyclers, e-waste aggregators, IT asset disposition providers, manufacturers, and OEMs. The demonstration facility will continue to support process development and operator training.

Built to Scale: One Purification Hub, Up to Five Regional Plants

The planned purification plant will be designed to process concentrate from up to five pre-concentration plants. Modern Mining’s growth strategy is a two-step model: regional pre-concentration plants near electronic waste suppliers, feeding centralized purification in North Carolina, an approach the Company believes could reduce transportation and overall operating costs.

Beyond the anticipated commissioning of the first plant, the Company plans to develop its expansion roadmap and begin research to improve recovery rates, reduce costs and evaluate additional metals and feedstocks.